title: How we build your shower
description: Every stage of a shower demolition and installation, in the order we do it.
duration-total: about 13 working days, demolition through glass
stage-count: 10
# stages
01 Preparation Day 1
City permits and inspections handled by us if needed. Most showers do not
require them.
Home flooring protected with Ram Board throughout the workspace.
02 Demolition Day 2
Old shower walls, floor, and sheetrock removed and disposed of.
Clean, organized demolition.
03 Framing adjustments Day 3
Existing framing modified and reinforced.
Old curb removed and floor lowered for a curbless design.
Solid wood blocking added between the studs at grab bar heights, so bars
anchor into structure rather than board. Last chance without reopening
the wall, and worth adding even if the bars come later.
Exhaust fan, lighting, or switch changes are wired while the walls are
open; the customer should raise them before demolition.
04 Plumbing upgrades Day 4
Drain and shower valve adjusted for correct height, depth, and alignment.
On a tub-to-shower conversion the valve moves up from tub height and the old
tub plumbing comes out.
Required shower pan inspection performed.
05 Wall insulation Day 5
Shower walls insulated for moisture control and comfort, if needed.
Conditional: not every shower needs it. Skipping it saves a project day.
06 Waterproof system Day 6
Waterproof board installed on every wall and the base. Depending on the
project we use Hydro Block or Schluter KERDI-BOARD.
All seams and connections sealed.
07 Base template Day 7
Shower base templated on site, after the waterproofing is complete.
The base is cut to the template, not to a drawing.
08 Stone fabrication and install Days 8 to 13
Order matters: the base is fabricated and installed first. With the base
set, the walls are templated, then fabricated, then installed.
The base is either tile or solid stone. A solid stone base adds 2 to 3 days
for fabrication and installation.
Exposed panel edges are capped with Schluter edge trim, matched to the
hardware finish, so every visible edge ends in a clean metal profile
instead of a raw cut.
09 Shower glass door system Day 14
Frameless glass panels templated, fabricated, and installed.
Hardware finish chosen by the customer: brushed nickel, chrome, gold, or
matte black.
10 Final finishing touches Day 15
Sheetrock patching and wall repair.
Paint touch-ups and blending.
Caulking as needed.
Full job-site cleaning.
# sequence facts
- The base is installed before the walls are templated.
- Templating happens after waterproofing, on site.
- Grab bar blocking is a stage 3 decision, not a stage 9 decision.
- Insulation is conditional and shifts the day numbers when skipped.
# photos
The human view of this page carries 11 photographs from one real project:
original shower, wall stripped to studs, framing marked for added 2x4s, valve
marked to be raised, insulation with grab bar blocking, waterproof board,
base template, wall templates, and the finished stone.
# pages
/ Site index. What Crowley's does and where each page leads.
/process/ The ten-stage shower build, day by day, with photos.
/materials/ What shower wall panels are made from, and what is refused.
/colors/ Every stocked slab color, with zoomable photos.
/checklist/ Printable homeowner checklist, keyed to build stage.
/projects/ Finished showers, with before and after photos.
/contact/ Estimate request form.
# contact
business: Crowley's Granite & Quartz
phone: 503-676-5136 (call or text)
licensed: Oregon CCB #237210, Washington #CROWLGC796M3
service-area: Portland, Oregon metro area
estimates: free
estimate-form: https://portlandshowerwalls.com/contact/